QualRotate Machinery SH
Jiangsu Helen Petrochemical CG-411-PTA Reactor Feed Pump Skid Project
Company News

Jiangsu Helen Petrochemical CG-411-PTA Reactor Feed Pump Skid Project

Date: Feb 19, 2025
Source: QualRotate

Project Background: This project is a key initiative in Jiangyin City for 2024. with QualRotate providing the skid-mounted design and implementation for the CG-411-PTA reactor feed pump. It will introduce the most advanced international processes and technologies to build China’s first PTA production facility with an annual capacity of 3.2 million tons. The project aims to establish a large-scale PTA industrial production base in China. It is the world largest high speed pump for PTA, with a total investment of 5 billion RMB and a implementation period of one year. Due to QualRotate’s involvement, the project achieved savings of 20 million RMB for the client.

• Reactor Feed Pump (Main Unit): Multi-stage high-speed gear pump (currently the world’s largest design specification).

• QualRotate's Contribution: Providing localized skid-mounted design and implementation solutions for the reactor feed pump.


Core Design Highlights:

1. Driver: Equipped with a 10kV air-cooled, self-circulating energy-saving motor.

2. Sealing System: Configured with P54+P32 water seal station, with a sealing pressure rating of 15 MPa.

3. Lubrication and Cooling System: Features a high-rigidity, compact integrated base for the main unit, oil tank, heat exchanger, and motor.

4. Instrumentation and Control System: Configured with a BN3500 online monitoring system, along with temperature, flow, and pressure control valves and transmitters.


Jiangsu Helen Petrochemical CG-411-PTA Reactor Feed Pump Skid Project


Design Capabilities:

• Lubrication system design

• Sealing system design

• Base structure design

• Motor design and selection


Implementation Capabilities:

• Manufacturing, installation, and commissioning of electromechanical and instrumentation equipment

• Prefabrication, welding, and hydrostatic testing of pressure pipelines

• Pickling and passivation of process pipelines

• Coating, packaging, large-scale hoisting, and transportation



Jiangsu Helen Petrochemical CG-411-PTA Reactor Feed Pump Skid Project


Quality Standards:

1. Integrated Base: Straightness of 0.02 mm/m for a base size of 7500 × 3300 mm.

2. Process Pipelines: Φ219×24 316L pipelines with 100% RT non-destructive testing pass rate.

3. Hydrostatic Testing: 100% first-pass qualification rate for process pipelines.

4. Axial and Radial Alignment: Precision of 0.01 mm between the main unit and the driver.

5. Compliance with the highest industry standards and specifications.


Scope of QualRotate's Work:

QualRotate's responsibilities cover design, manufacturing, assembly, inspection, testing, and on-site services for the project. This includes electromechanical and instrumentation commissioning for both single-unit and integrated systems.


Delivery Timeline:

The project spans 12 months, with a total of 4 sets to be delivered.


Jiangsu Helen Petrochemical CG-411-PTA Reactor Feed Pump Skid Project


NEXT: No information
More News
How QualRotate Defines Reliability: Reliability Comes from a Complete Engineering Chain
20 Apr 2026
Why can a compressor run reliably over the long term? It depends not on one component or one test alone, but on whether the full engineering chain truly works as a closed loop.
Learn More
Offshore Oil & Gas Scenarios: Common Requirements Imposed by the Marine Environment on Centrifugal Compressors
19 Dec 2025
Offshore oil and gas facilities operate under harsh marine conditions such as high humidity, salt spray, environmental disturbances, and space constraints. This article explores how these factors shape the reliability, integration, and long-term operation requirements of centrifugal compressors in offshore applications.
Learn More
QualRotate Showcases Integrated Solutions for Rotating Equipment at OGA 2026
Learn More
11 Sep. 2026
On September 2, 2026, the Malaysia Oil, Gas & Energy Exhibition (OGA 2026) officially opened in Kuala Lumpur, Malaysia. QualRotate participated in the exhibition, engaging with clients, partners, and industry professionals from across the global oil, gas, and energy sectors.
Balancing Within Micron-Level Clearances: How Dry Gas Seals Control Compressor Leakage
Learn More
05 Aug. 2026
Dry gas seals build micron‑thick gas films to keep seal faces non‑contact, achieving controlled micro‑leakage and solving shaft‑end sealing contradictions for centrifugal compressors.
QualRotate Participates in OC2026, Exploring Compressor Solutions for Offshore Oil and Gas Applications
Learn More
25 Jun. 2026
On June16-17, QualRotate participated in OC2026 in Shenzhen,showcasing compressor technologies and offshore oil and gas solutions while engaging with operators, FPSO-related companies, offshore engineering contractors and EPC partners.
We use cookies to offer you a better browsing experience, analyze site traffic and personalize content. Part of the tracking is necessary to ensure SEO effectiveness,
By using this site, you agree to our use of cookies. Visit our cookie policy to learn more.
Reject Accept